Slowly ticking boxes and getting things hooked up.
Propane mounts finished and the cabinet is finished. Only thing left to do here is run the lines.
Electrical cabinet layout is all set. All that is left here is to cut a bunch of cables and connect everything together. I decided to space everything out so I never have to fight with with wiring in a cramped setting.
For reference-
Top Shelf: Inverter, Blank space in middle will hold Ryobi charger, shore power AC battery charger
Middle Shelf: Solar charge controller, House battery fuse box, master fuses, battery
Bottom Shelf: 7 pin trailer power distribution, small charger for breakaway battery, breakaway controller.
Had to run some wires in preparation for the solar panels. Keeping wires out of trouble is not an easy task on a telescoping roof as it turns out. Solution presented itself in the form of a large drag chain made for a CNC machine. Houses the solar wiring and will flex in one direction when the roof is lowered.