So I'm in the process of installing 4 solar panels (200w, 24v open circuit, Rich Solar mono) atop our little 15A Escape trailer. Due to the small amount of real estate I'm stacking 2 panels atop each other, at each end of the trailer's roof, with the top panels mounted to full extension drawer slides. So 2 of the 200w panels will be full timers with other 2 panels, mounted below each of the full time panels, to be slid out when in stationary camp mode.
I am thinking of connecting the two stacked panels in parallel then the 2 pairs in series. Reasoning: With the lower panel being basically in the dark until the upper panel is pulled out, it should, since its in parallel, allow the full time panel to operate at it's max capability.
So 2P2S. All are managed by a Victron 50/100 MPPT controller.
Am I on the right path?
Thanks!
I am thinking of connecting the two stacked panels in parallel then the 2 pairs in series. Reasoning: With the lower panel being basically in the dark until the upper panel is pulled out, it should, since its in parallel, allow the full time panel to operate at it's max capability.
So 2P2S. All are managed by a Victron 50/100 MPPT controller.
Am I on the right path?
Thanks!